Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Danish TSO Finishes Grid Connection for Thor Offshore Wind Farm
Grid Connection

June 18, 2025 · about 1 year ago

Danish TSO Finishes Grid Connection for Thor Offshore Wind Farm

Danish transmission system operator (TSO) Energinet has completed the construction work related to the connection of the 1 GW Thor offshore wind farm to the national grid. The construction work began in January 2023 and has been completed on time, said Energinet. The scope of work included moving 95

2 minutes read
  • LinkedIn
  • X
  • Email
Danish TSO Energinet Thor grid connection
Photo: NCC

Danish transmission system operator (TSO) Energinet has completed the construction work related to the connection of the 1 GW Thor offshore wind farm to the national grid.

The construction work began in January 2023 and has been completed on time, said Energinet. The scope of work included moving 95,000 cubic metres of soil and laying 150 cable drums, each weighing 25 tonnes.

Renewable energy will be transported offshore through two 220 kV substations located at Volder Mark and Idomlund near Holstebro, via a 30-kilometre twin cable system. Due to environmental restrictions, seven kilometres of the cable were installed using underground drilling.

“In Energinet, we are now ready with our part of the project, so that we can help the green electricity out into the country. This will happen through our station in Idomlund and out onto the high-voltage grid to consumers in both Denmark and our neighboring countries. It is a huge milestone that we have been looking forward to,” said Søren Dupont Kristensen , Chief Operating Officer at Energinet.

Related Articles

Cables

Onshore Cabling Work for Denmark’s Largest Offshore Wind Farm Starts

2 min read

Energinet added that it has finished on time, despite several challenges along the way. The weather has been rainy, the environmental approval came late (not until 2022), and the war in Ukraine led to a shift in the supplier market, which affected time and finances, according to the TSO.

“The environmental approval had many restrictions because there were several areas with vulnerable nature. This meant that we had to drill under some of the cables, and then there was also the stork Keld, who had settled in Bækmarksbro. He was monitored day and night and Energinet was not allowed to work in the area from March to October,” said Martin Hinrichsen , Chief Project Manager at Energinet.

The TSO expects the first of 72 Siemens Gamesa SG 14-236 DD wind turbines to start generating electricity in 2026.

The first monopiles are already installed at the site located approximately 22 kilometres off the west coast of Jutland.

RWE, which is leading the construction and operation of the offshore wind farm on behalf of its partnership with Norges Bank Investment Management, plans to have Thor up and running by the end of 2027.

Related Articles

Fixed-Bottom

Thor O&M Base Almost Completed

1 min read

LinkedIn X Facebook Google News

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionOnshore InfrastructureProject UpdatesWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free