Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›Dutch Gov’t Shelves Two Offshore Wind Tenders, Plans Single Site Auction
Authorities

May 19, 2025 · about 1 year ago

Dutch Gov’t Shelves Two Offshore Wind Tenders, Plans Single Site Auction

Citing deteriorating market conditions, the Dutch government has delayed tenders for two offshore wind farms and will instead open a tender for one location in the North Sea later this year. The tenders for IJmuiden Ver Gamma-A and IJmuiden Ver Gamma-B were scheduled for the third quarter of this ye

2 minutes read
  • LinkedIn
  • X
  • Email
tender sites Nederwiek I-A dutch
Source: Netherlands Enterprise Agency

Citing deteriorating market conditions, the Dutch government has delayed tenders for two offshore wind farms and will instead open a tender for one location in the North Sea later this year.

The tenders for IJmuiden Ver Gamma-A and IJmuiden Ver Gamma-B were scheduled for the third quarter of this year. However, due to deteriorating market conditions and decreased demand for electricity, the two sites will be tendered later, said the government.

The Dutch government plans to open a tender for the Nederwiek I-A site, located 95 kilometres from the west coast of Texel, in October 2025. The site is part of a larger area within the Nederwiek Wind Farm Zone.

Initially, the Nederwiek I-A site was planned to accommodate a 2 GW offshore wind farm, but the site size was decreased to 1 GW. This is said to reduce the investment required per site and the financial risks for wind farm developers.

Related Articles

Authorities

Dutch Gov’t Splits Offshore Wind Areas for Upcoming Tender Into Four 1 GW Sites

2 min read

In addition, the government has eased the rules and criteria for the upcoming tender by capping the maximum liability for developers during the first two years after a permit is awarded. Within that period, developers may request the minister to revoke the permit in exchange for the bank guarantee if market conditions prove too unfavorable to proceed with the project.

To reduce application costs for developers, the ranking criteria for bid assessment have been simplified, according to the Dutch Climate Ministry.

The government said it is working on an action plan for offshore wind that can improve the investment climate. Financial support instruments will be considered, such as a minimum and maximum price guarantee (Contract for Difference) from 2027 onwards, the government added.

At the beginning of this year, the Dutch Ministry of Climate and Green Growth announced that it is exploring which procedure to choose for the permitting of the Nederwiek II and Nederwiek III offshore wind sites that are planned to be put out to tender in 2026.

The 2026 offshore wind tender in the Netherlands will be held for three sites, Nederwiek IB, Nederwiek II, and Nederwiek III.

Related Articles

Authorities

Netherlands Consulting Developers on 2026 Offshore Wind Tender

2 min read

LinkedIn X Facebook Google News

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

AuthoritiesPlanning & Permitting

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free