Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›OES Group to Protect Inch Cape Monopile Foundations
Business & Finance

March 13, 2025 · about 1 year ago

OES Group to Protect Inch Cape Monopile Foundations

Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, has awarded a contract to OES Group to supply 54 external and internal Impressed Current Cathodic Protection (ICCP) systems to protect the offshore wind project’s monopile and transition piece foundations. The IC

1 minutes read
  • LinkedIn
  • X
  • Email
OES Group to Protect Inch Cape Monopile Foundations
Image source: Inch Cape Offshore Limited

Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, has awarded a contract to OES Group to supply 54 external and internal Impressed Current Cathodic Protection (ICCP) systems to protect the offshore wind project’s monopile and transition piece foundations.

The ICCC anodes will be produced in OES Group’s new dedicated 5,000-square-metre facility in Gateshead, the UK, and will be shipped to two fabrication yards located in China.

The first systems are planned to leave in as little as two weeks, of which 20 per month will be produced to support the rapid fabrication schedule of the Inch Cape offshore wind project, said the company.

OES will further support installation in China and Forth Ports Leith Harbour before moving the systems offshore for final installation and commissioning.

Located 15 kilometres off the East Coast of Scotland, the Inch Cape offshore wind farm covers a total area of 150 square kilometres.

The 1,080 MW project will feature 72 Vestas V236-15.0 MW turbines installed on a mix of monopile and jacket foundations, an offshore substation, and two 85-kilometre AC export cables, delivering power to an onshore substation , currently under construction at Cockenzie, East Lothian.

The wind farm is expected to produce its first power in late 2026 and to be fully commissioned in 2027.

Related Articles

Cables

Inch Cape Offshore Construction to Start in April

2 min read

LinkedIn X Facebook Google News

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceContracts & TendersSupply Chain

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1EDF Buys RWE’s Stake in 1.1 GW UK Offshore Wind Farm
  2. 2Norway Revises Utsira Nord Floating Wind Support Terms
  3. 3Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  4. 4Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free