Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›UK Company to Deliver Davit Cranes for Inch Cape Offshore Wind Farm
Business & Finance

February 11, 2025 · about 1 year ago

UK Company to Deliver Davit Cranes for Inch Cape Offshore Wind Farm

The developer of the Inch Cape offshore wind farm has awarded a contract to UK-based Granada Cranes to provide 72 davit crane units on one of Scotland’s largest offshore wind projects. Granada Cranes has been contracted to design and supply two separate types of davit cranes, each to suit the mixed

2 minutes read
  • LinkedIn
  • X
  • Email
Inch Cape
Source: Granada Cranes

The developer of the Inch Cape offshore wind farm has awarded a contract to UK-based Granada Cranes to provide 72 davit crane units on one of Scotland’s largest offshore wind projects.

Granada Cranes has been contracted to design and supply two separate types of davit cranes, each to suit the mixed use of jacket and monopile foundation type design.

The company has already delivered a single davit crane for the offshore substation in 2024.

Granada Cranes is now looking to place orders and subcontract specialist areas of work to other local businesses, according to the company.

Production of the first batches from the factory is expected in the second quarter of 2025, and deliveries will continue until the end of the year.

Last month, Red Rock Renewables and ESB reached a financial close on the 1,080 MW Inch Cape offshore wind farm in Scotland.

Inch Cape was first awarded planning consent in 2014. The offshore wind farm has a 50-year lease with Crown Estate Scotland and has secured 15-year contracts with the Low Carbon Contracts Company (LCCC) through the UK government’s Contract for Difference (CfD) auctions in 2022 and 2024 .

The project will feature 72 Vestas V236-15.0 MW turbines installed on a mix of monopile and jacket foundations, a single offshore substation platform, and two 85-kilometre AC export cables, delivering power to an onshore substation , currently under construction at Cockenzie, East Lothian.

The first power is expected in late 2026, with a commercial operation date in 2027.

Related Articles

Business & Finance

1.1 GW Inch Cape Wind Farm Entering Offshore Construction Phase

3 min read

LinkedIn X Facebook Google News

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceContracts & TendersFixed-BottomSupply Chain

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Gennaker Offshore Substation Topsides Loaded Out Ahead of Sail-Away
  2. 2RWE Takes FID on 400 MW Battery Storage to Support Dutch OranjeWind Offshore Wind Farm
  3. 3Gazelle Tests Floating Wind Platform for 18+ MW Turbines in Typhoon Conditions
  4. 4US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution Wind

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free