Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fixed-Bottom›Cost of CVOW Project Rises to USD 10.7 Billion, Completion on Track for 2026
Fixed-Bottom

February 4, 2025 · about 1 year ago

Cost of CVOW Project Rises to USD 10.7 Billion, Completion on Track for 2026

On 3 February, Dominion Energy announced that the estimated total costs for the Coastal Virginia Offshore Wind (CVOW) project have increased by nine per cent. In addition, the developer said that the 2.6 GW wind farm is now approximately 50 per cent complete and remains on track for on-time completi

2 minutes read
  • LinkedIn
  • X
  • Email
CVOW costs
Source: Dominion Energy

On 3 February, Dominion Energy announced that the estimated total costs for the Coastal Virginia Offshore Wind (CVOW) project have increased by nine per cent. In addition, the developer said that the 2.6 GW wind farm is now approximately 50 per cent complete and remains on track for on-time completion at the end of 2026.

The estimated total project costs, including contingency but excluding financing costs, have risen by about nine per cent, from USD 9.8 billion to USD 10.7 billion, marking the first and only increase since the initial budget was submitted to the Virginia State Corporation Commission (SCC) in November 2021, said Dominion.

According to the company, the increase comes as a result of higher network upgrade costs, which are assigned by regional electric grid operator PJM, and higher onshore electrical interconnection costs.

Aside from changes to onshore expenses, aggregate costs for other project elements, including offshore, have remained in line with the original budget, stated the developer.

Related Articles

Fixed-Bottom

First Installation Campaign at 2.6 GW Coastal Virginia Offshore Wind Project Completed

2 min read

As a result of the comprehensive stakeholder agreement, 50 per cent of the updated total project costs above USD 10.3 billion are unrecoverable from customers and borne by the project owner, according to the company. As a result, the expected average impact over the life of the offshore wind project on a typical residential customer bill using 1,000 KWh per month is a 43 cent per month increase, said Dominion.

As part of a business review, Dominion Energy completed non-controlling equity financing with Stonepeak, where the company will cover 50 per cent of project costs up to USD 11.3 billion and share additional costs beyond that amount. This means Stonepeak will fund half, or about USD 450 million, of the USD 900 million increase in total project expenses, according to Dominion.

Coastal Virginia Offshore Wind Project Remains on Track

Dominion revealed that the project is now about 50 per cent complete and remains on track for on-time completion at the end of 2026.

The first 16 transition pieces (TPs) have been installed at the CVOW project site, located some 43 kilometres off the coast of Virginia Beach. The TPs are being installed on the 176 monopiles that are manufactured and delivered by EEW SPC.

Delivery of the first of three 4,300-tonne offshore substations to the Portsmouth Marine Terminal in Virginia Beach happened at the end of January.

Related Articles

Fixed-Bottom

US Port Welcomes First Coastal Virginia Offshore Substation

2 min read

Fully fabricated monopiles, transition pieces, undersea cable, and other major components continue to be delivered in preparation for on-schedule installation. Wind turbine tower and blade fabrication is now underway, with nacelle fabrication to begin later this quarter.

Charybdis , the American-built, flagged, and crewed wind turbine installation vessel (WTIV), has commenced sea trials in Brownsville, Texas, according to Dominion.

The 2.6 GW CVOW will feature 176 Siemens Gamesa 14 MW wind turbines and will become the biggest US offshore wind farm once in operation.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Fixed-BottomProject UpdatesWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free