Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Dutch Offshore Wind Farm Fully Online After Cable Repair Fix
Operations & Maintenance

September 23, 2024 · about 2 years ago

Dutch Offshore Wind Farm Fully Online After Cable Repair Fix

The 600 MW Gemini wind farm offshore the Netherlands is once again fully operational after experiencing a failure in one of the export cables between the wind farm and the shore. A group of cable and energy specialists, including a repair team from NKT, helped Gemini with a fast repair during the su

1 minutes read
  • LinkedIn
  • X
  • Email
Faulty cable at Gemini offshore wind farm
NKT

The 600 MW Gemini wind farm offshore the Netherlands is once again fully operational after experiencing a failure in one of the export cables between the wind farm and the shore.

A group of cable and energy specialists, including a repair team from NKT, helped Gemini with a fast repair during the summer. The NKT team was responsible for the jointing of the replacement cable between the wind farm and the coast.

”NKT is pleased to have contributed to the swift repair of the Gemini connection, bringing the wind park back to full operational capacity and supplying sustainable energy to households across the Netherlands. Restoring a subsea connection is a complex operation that requires significant skills and expertise. We greatly appreciated the strong collaboration with the Gemini team on the job execution,” said Axel Barnekow Widmark , Executive Vice President, Service & Installation at NKT.

Located 85 kilometres north of the Groningen coast, Gemini comprises 150 Siemens 4MW turbines and two offshore substations, Buitengaats and ZeeEnergie.

The 600 MW offshore wind farm was officially opened in early May 2017.

The project’s stakeholders include Northland Power (60%), Siemens Project Ventures (20%), HVC (10%) and ALTE LEIPZIGER-HALLESCHE group (10%).

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Operations & MaintenanceProject UpdatesWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free