Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cables›Export Cable Installation Completed at 30 MW EolMed Floating Wind Farm in France
Cables

May 30, 2024 · about 2 years ago

Export Cable Installation Completed at 30 MW EolMed Floating Wind Farm in France

Italy-headquartered Prysmian has completed the installation of the export cable for the 30 MW Gruissan/EolMed floating offshore wind project in France. In 2021, Prysmian signed a contract with the French transmission system operator (TSO) Réseau de Transport d’Électricité (RTE) for the Engineering,

2 minutes read
  • LinkedIn
  • X
  • Email
Thor Wind Turbine
Thor Wind TurbineIllustration: The project area for the Jammerland Bugt Coastal Offshore Wind Farm; Source: The Danish Energy Agency

Italy-headquartered Prysmian has completed the installation of the export cable for the 30 MW Gruissan/EolMed floating offshore wind project in France.

In 2021, Prysmian signed a contract with the French transmission system operator (TSO) Réseau de Transport d’Électricité (RTE) for the Engineering, Procurement, Construction, and Installation (EPCI) of an export submarine power cable system.

Related Articles

Contracts & Tenders

Prysmian and Asso.subsea Secure Floating Wind Contract in France

2 min read

The company was responsible for the design, supply, installation, termination, testing, and commissioning of a 66 kV static three-core export submarine cable with EPR insulation for a total of 23 kilometres.

In addition, Prysmian also supplied and installed a 66 kV dynamic submarine export tail with EPR insulation connecting the onshore grid to the floating electrical hub (FEH) of EolMed’s floating wind farm, which is currently under construction .

Bourbon Subsea Services installed the floating electrical hub in January 2024. According to information available online, the construction of the FEH was performed by the Cyprus-based company Multimarine Services.

“With this project, which follows Provence Grand Large (PGL) floating offshore wind farm, Prysmian demonstrates once again its leading position in the market and the validity of its know-how and technologies in the development of submarine cables and systems to support smarter and greener power grids worldwide,” said Alberto Boffelli , COO Transmission, Prysmian.

YOU MIGHT ALSO LIKE

The EolMed floating wind farm will comprise three Vestas V164-10.0 MW wind turbines mounted on BW Ideol’s Damping pool floating foundations and installed 15 kilometres off Gruissan, in water depths of around 60 metres.

The project, being developed by Qair, TotalEnergies, and BW Ideol, was planned to be commissioned in mid-2024.

The installation of the floaters at the project site is now expected to start in June 2025 and the final commissioning is anticipated to take place in the third quarter of next year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

CablesFloating WindGrid ConnectionProject UpdatesWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1New Study Identifies Foundation Standardisation, Lower Cost of Capital as Key to Floating Wind Competitiveness
  2. 2Subsea Micropiles to Work on Anchor Design for Pentland Floating Wind Farm
  3. 3Equinor Assembles Celtic Sea Offshore Wind Scoping Report Team
  4. 4Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free