Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›Ørsted and New Jersey Reach USD 125 Million Settlement Over Scrapped Offshore Wind Projects
Authorities

May 29, 2024 · about 2 years ago

Ørsted and New Jersey Reach USD 125 Million Settlement Over Scrapped Offshore Wind Projects

Danish renewable energy developer Ørsted will pay New Jersey USD 125 million (approximately EUR 115 million) to settle claims over the company’s cancellation of two offshore wind farm projects, Ocean Wind 1 and Ocean Wind 2, last year. The state’s Board of Public Utilities (BPU) said the USD 125 mil

1 minutes read
  • LinkedIn
  • X
  • Email
Ørsted and New Jersey Reach USD 125 Million Settlement Over Scrapped Offshore Wind Projects
Illustration; Hornsea One offshore wind farm; Photo: Ørsted

Danish renewable energy developer Ørsted will pay New Jersey USD 125 million (approximately EUR 115 million) to settle claims over the company’s cancellation of two offshore wind farm projects, Ocean Wind 1 and Ocean Wind 2, last year.

The state’s Board of Public Utilities (BPU) said the USD 125 million it will receive will be used to support investments in wind energy facilities, component manufacturing facilities, and other clean energy programmes.

Last July, New Jersey Governor Phil Murphy signed a bill that would have allowed Ørsted to retain federal tax credits.

Related Articles

Authorities

Ørsted Gets Tax Break for New Jersey’s First Offshore Wind Farm, Shell-EDF JV Calls for Same Treatment for All Current NJ Projects

4 min read

Before the projects were abandoned, Ørsted had provided a USD 100 million guarantee to complete one of them, Ocean Wind 1, by the end of 2025. Additionally, the company was obligated to contribute USD 200 million toward developing the offshore wind industry in New Jersey.

According to the developer, supply chain disruptions, rising interest rates, and inflation were some of the causes of the discontinuation of the Ocean Wind 1 and Ocean Wind 2 offshore wind projects.

Located about 24 kilometres southeast of Atlantic City, the 1.1 GW Ocean Wind 1 was planned to feature 98 Haliade-X 12 MW wind turbines and up to three offshore substations within its lease area.

Related Articles

Business & Finance

Ørsted Cancels Two Wind Projects Offshore New Jersey, Clears Revolution Wind for Takeoff

3 min read

Last November, the company wrote off almost EUR 3.8 billion , due largely to costs associated with the cancellation of its two offshore wind projects (DKK 19.9 billion).

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

AuthoritiesBusiness & FinancePlanning & Permitting

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free