Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business development›Dutch Gov’t Issues Offshore Wind Tender Teaser
Business development

February 26, 2024 · about 2 years ago

Dutch Gov’t Issues Offshore Wind Tender Teaser

The Netherlands Enterprise Agency (RVO) plans to publish a European tender in the first half of April for geotechnical surveys of the Huibertgat and Ballonplaat sites in the Netherlands. The objective of the tender is to conclude an agreement with one or more tenderers who can carry out geotechnical

2 minutes read
  • LinkedIn
  • X
  • Email
Dutch Gov’t Issues Offshore Wind Tender Teaser
Photo for illustrative purpose only; Hollandse Kust Zuid offshore wind farm in the Netherlands; Photo source: Vattenfall

The Netherlands Enterprise Agency (RVO) plans to publish a European tender in the first half of April for geotechnical surveys of the Huibertgat and Ballonplaat sites in the Netherlands.

The objective of the tender is to conclude an agreement with one or more tenderers who can carry out geotechnical investigations at the nearshore Huibertgat and on the Ballonplaat to the north of Rottumerplaat, the Netherlands.

The European tender will consist of two different lots, divided on the basis of water depth and workability, according to the prior information notice RVO issued on 26 February.

The exact scope of work is planned to be determined in the near future, but both cone penetration tests (CPT) and borehole sampling are anticipated for both lots, according to RVO.

Both investigations are planned to be executed in the third quarter of 2024.

The results of the geotechnical investigations are part of the Eemshaven Offshore Wind Energy Connection Programme (Programma Aansluiting Wind op Zee, PAWOZ Eemshaven) and will be used for a feasibility study.

PAWOZ investigates the possibilities for future cable and pipeline routes from the North Sea to Eemshaven.

The programme is exploring the possibilities of connecting 4.7 GW of offshore wind energy to the grid by the end of 2031 as well as options beyond that, according to RVO.

latest news

The Netherlands aims to have 21 GW of operating offshore wind capacity by 2030, corresponding to around 75 per cent of the country’s current electricity consumption.

While working on bringing the installed capacity to 21 GW over the following several years, the Dutch government will also get busy with realising its offshore wind target set for 2050, by when the Netherlands is planned to have 70 GW of offshore wind installed in its North Sea waters.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business developmentGrid ConnectionInfrastructureResearch & Development

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Gov’t Seeks New Review of US Wind’s Maryland Project
  2. 2Former RWE Offshore Wind CEO Joins Esvagt Board
  3. 3UK’s First HVDC Subsea Cable Factory Opens in Scotland
  4. 4Diverse Marine to Build Three More CTVs for OEG

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free