Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cables›Van Oord Installs All Baltic Eagle Foundations and Inter-Array Cables
Cables

December 20, 2023 · about 2 years ago

Van Oord Installs All Baltic Eagle Foundations and Inter-Array Cables

Van Oord has completed the installation of all foundations and inter-array cables at Iberdrola’s Baltic Eagle offshore wind farm in the German sector of the Baltic Sea. The heavy-lift installation vessel Svanen installed the final monopile in September and the company has now put all the transition

1 minutes read
  • LinkedIn
  • X
  • Email
Van Oord Installs All Baltic Eagle Foundations and Inter-Array Cables
Van Oord

Van Oord has completed the installation of all foundations and inter-array cables at Iberdrola’s Baltic Eagle offshore wind farm in the German sector of the Baltic Sea.

The heavy-lift installation vessel Svanen installed the final monopile in September and the company has now put all the transition pieces (TPs) in place. The TPs were installed in two campaigns with Van Oord utilising Spliethoff’s Brouwersgracht and Jumbo’s Fairplayer vessels to perform the work.

Related Articles

Fixed-Bottom

All Monopiles Stand at Iberdrola’s Baltic Eagle Wind Farm Offshore Germany

2 min read

Furthermore, Van Oord, using its cable-laying vessel Nexus , has also completed the installation of the inter-array cables that started in October.

The company’s remotely-operated trencher Dig-It buried the inter-array cables to the required depth and the termination and testing works on the inter-array cables are now in full swing, and are expected to be completed in the first quarter of 2024.

Related Articles

Fixed-Bottom

Van Oord Begins Cable Installation Activities at Iberdrola’s Baltic Eagle

2 min read

The Baltic Eagle offshore wind farm will comprise 50 Vestas 9.5 MW wind turbines , installed on monopile foundations, and will be linked to the German high-voltage grid via the Ostwind 2 grid connection.

Scheduled to be fully operational by the end of 2024, the 476 MW wind farm will supply approximately 475,000 households with renewable energy while reducing CO2 emissions by approximately 800,000 tonnes per year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

CablesFixed-BottomFoundationsGrid ConnectionProject UpdatesSupply ChainVesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution Wind
  2. 2Vietnam-Made Cable Layer Enters Into Service in Taiwan
  3. 3Germany’s 960 MW He Dreiht Offshore Wind Farm Inaugurated
  4. 4200th Vestas V236-15.0 MW Wind Turbine Installed Offshore

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free