Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Amprion Picks Steel Contractor for Offshore Converter Platforms
Contracts & Tenders

November 22, 2023 · about 2 years ago

Amprion Picks Steel Contractor for Offshore Converter Platforms

German shipbuilding company, Meyer Werft, has been awarded its first contract for steel construction work for four Amprion offshore converter platforms. Amprion Offshore has commissioned Dragados Offshore and Siemens Energy to build the offshore converter platforms. The consortium has now awarded pa

2 minutes read
  • LinkedIn
  • X
  • Email
Amprion Meyer Werft
Source: Meyer Werft

German shipbuilding company, Meyer Werft, has been awarded its first contract for steel construction work for four Amprion offshore converter platforms.

Amprion Offshore has commissioned Dragados Offshore and Siemens Energy to build the offshore converter platforms.

The consortium has now awarded parts of the production to Meyer Werft.

Related Articles

Contracts & Tenders

Siemens Energy Consortium Nets EUR 4 Billion Offshore Wind Power Grid Deal

2 min read

Amprion said that the shipyard is to produce around 43,500 tonnes of steel components for the four grid connection systems DolWin4 and BorWin4 as well as BalWin1 and BalWin2 in the North Sea.

Of this, around 32,000 tonnes are used to produce sections for the BalWin1 and BalWin2 projects, while for the DolWin4 and BorWin4, it is around 11,500 tonnes.

The components are planned to be delivered from autumn 2024 to spring 2027.

The contract marks Meyer Werft’s entry into the offshore wind market.

“This order is a milestone for us in our entry into the construction of converter platforms, which we will also build at NEPTUN WERFT in Rostock in the future. This successful expansion of our product portfolio secures knowledge and employment at our German shipyards and at the same time makes a decisive contribution to the energy transition,” said Jan Meyer , Managing Director of Meyer Werft.

The four offshore grid connection systems DolWin4 and BorWin4 as well as BalWin1 and BalWin2 connect wind farms in the North Sea with the transmission grid on land. They are installed largely parallel to each other on both the land and sea sides, said Amprion.

YOU MIGHT ALSO LIKE

The DolWin4 and BorWin4 projects will transmit together a power of 1.8 GW and are scheduled to go into operation in 2028.

BalWin1 and BalWin2, each capable of transmitting 2 GW, are scheduled to go into operation in 2029 and 2030, respectively.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & TendersEquipmentGrid ConnectionManufacturingOffshore PlatformsSupply Chain

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Bibby Marine Launches Battery-First eCSOV in Spain
  2. 2Ørsted to Buy Back Remaining Stake in Gunfleet Sands Offshore Wind Farm
  3. 3EDF Buys RWE’s Stake in 1.1 GW UK Offshore Wind Farm
  4. 4Norway Revises Utsira Nord Floating Wind Support Terms

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free