Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Foundation, Inter-Array Cable Laying Work Completed at 759 MW Dutch Offshore Wind Farm
Wind Farm Update

June 9, 2023 · about 3 years ago

Foundation, Inter-Array Cable Laying Work Completed at 759 MW Dutch Offshore Wind Farm

Van Oord has equipped foundations at the Hollandse Kust Noord offshore wind farm with secondary steel and installed all inter-array cables, with cable burial and wind turbine installation underway at the 759 MW Dutch offshore wind farm. Offshore installation vessel MPI Resolution has installed all s

1 minutes read
  • LinkedIn
  • X
  • Email
Foundation, Inter-Array Cable Laying Work Completed at 759 MW Dutch Offshore Wind Farm
Van Oord via LinkedIn

Van Oord has equipped foundations at the Hollandse Kust Noord offshore wind farm with secondary steel and installed all inter-array cables, with cable burial and wind turbine installation underway at the 759 MW Dutch offshore wind farm.

Offshore installation vessel MPI Resolution has installed all secondary steel and thus completed the wind turbine foundations. Cable-laying vessel Nexus has finished installing all inter-array cables, with cable burial still underway.

The installation of wind turbines is currently in full swing, the offshore construction company said on social media.

Van Oord, as a Balance of Plant contractor for the project, installed the first TP-less monopile at the project site in October last year and completed the installation of all 70 foundations at the beginning of this year.

Related Articles

Wind Farm Update

Final TP-Less Monopile In Place at Hollandse Kust Noord Offshore Wind Farm

2 min read

For the installation of the monopiles, produced by Sif Group, Van Oord engaged DEME and its jack-up vessel Innovation .

The first of the project’s 69 Siemens Gamesa 11 MW wind turbines was installed in April. Siemens Gamesa and Van Oord are using the offshore installation vessel Scyll a to transport and install the turbines.

Related Articles

Vessels

First Turbine Stands at Hollandse Kust Noord Offshore Wind Farm

2 min read

The Hollandse Kust Noord wind farm is being developed by CrossWind, a joint venture between Shell and Eneco. The wind farm is expected to supply the first electricity to the Dutch grid by the summer and full commissioning of the project is expected by the end of 2023.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Pacifico Energy Launches Survey Campaign for 1.8 GW Offshore Wind Projects in Vietnam
  2. 2Inter-Array Cable Installation About to Start at 2.9 GW UK Offshore Wind Farm
  3. 3Ørsted Orders Third Saab Seaeye Cougar ROV for Offshore Wind Operations
  4. 4Hampidjan Advant to Equip Cadeler's Wind Ace for East Anglia Two Job

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free