Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Vessels›Crane Incident Delays Delivery of Seaway Alfa Lift
Vessels

March 16, 2022 · about 4 years ago

Crane Incident Delays Delivery of Seaway Alfa Lift

The Seaway Alfa Lift foundation installation vessel is not expected to be operational on offshore wind projects during 2022, according to Stuart Fitzgerald, Chief Executive Officer of Seaway 7. As reported, Seaway Alfa Lift suffered an incident with the A-frame on the 3,000t Liebherr crane in Octobe

2 minutes read
  • LinkedIn
  • X
  • Email
A photo of Alfa Lift's crane being installed
Installation of the main crane on board Seaway Alfa Lift. Source: OHT

The Seaway Alfa Lift foundation installation vessel is not expected to be operational on offshore wind projects during 2022, according to Stuart Fitzgerald, Chief Executive Officer of Seaway 7.

As reported, Seaway Alfa Lift suffered an incident with the A-frame on the 3,000t Liebherr crane in October 2021.

Related Articles

Vessels

Crane Incident on Alfa Lift Installation Vessel

2 min read

The A-frame has since been removed from the vessel, inspected, and is now under repair at the China Merchants Heavy Industry (CMHI) shipyard in Jiangsu, China, where the vessel is under construction. Crane repairs are expected to be completed during the second half of 2022, Fitzgerald said.

”As a result of key supplier delays, the final installation, testing and commissioning of the mission equipment for the upending and lowering of monopiles is expected to represent the critical path to vessel delivery and readiness for operations,” Fitzgerald said.

”We do not expect the vessel will be operational on projects during 2022.”

Seaway Alfa Lift, which departed for sea trials in early January 2022, was initially scheduled to be delivered by the end of 2021 or in early 2022, in time to start her first assignment – the installation of monopile foundations at the Dogger Bank A wind farm offshore the UK in the second half of 2022.

”A contingency scenario is activated which utilises Seaway Strashnov to progress the committed work on the Dogger Bank A project in the second half of 2022,” Fitzgerald said.

Alfa Lift will also install the monopile foundations on the Dogger Bank B and Dogger Bank C phases of what is the world’s largest offshore wind farm under construction.

Related Articles

Contracts & Tenders

Seaway 7 Completes Dogger Bank Trifecta

2 min read

LinkedIn Twitter Facebook

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

VesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm
  2. 2Acta Marine Christens CSOV Chartered by Vestas
  3. 3New Owner to Continue Operations at German Offshore Wind Farm Previously Set for Decommissioning
  4. 4All Monopiles In at Nordlicht I Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free