Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Ports & Logistics›Foundations Stand at First Mediterranean Offshore Wind Farm
Ports & Logistics

January 13, 2022 · about 4 years ago

Foundations Stand at First Mediterranean Offshore Wind Farm

Van Oord’s jack-up MPI Resolution has installed the ten monopile foundations at the first wind farm to be built in the Mediterranean Sea – the 30 MW Taranto offshore wind farm. The Taranto offshore wind farm, also known as Beleolico, is located in Italy’s Apulia Region near the Taranto harbour. The

1 minutes read
  • LinkedIn
  • X
  • Email
A photo of the MPI Resolution vessel loading a monopile for the Taranto offshore wind farm in Italy
MPI Offshore

Van Oord’s jack-up MPI Resolution has installed the ten monopile foundations at the first wind farm to be built in the Mediterranean Sea – the 30 MW Taranto offshore wind farm.

The Taranto offshore wind farm, also known as Beleolico, is located in Italy’s Apulia Region near the Taranto harbour.

Related Articles

Vessels

Monopile Load-Out Starts for Italy’s First Offshore Wind Farm

1 min read

The wind farm will comprise ten MySE 3.0-135 wind turbines provided by MingYang Smart Energy.

Related Articles

Wind Farm Update

MingYang Turbines for Taranto OWF Arrive in Italy

1 min read

”At this moment preparations are being made for the installation of the turbines and the expectation is that this will be completed in February,” a spokesperson for Van Oord told offshore WIND.

MPI Resolution is in charge of installing the wind farm’s monopiles, secondary steel, and the wind turbines.

The wind farm is scheduled to be fully commissioned in 2022 and provide about 55,600 MWh of electricity per year, enough to meet the demand of around 18,500 households, Renexia SpA, the developer of the project, said.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Ports & LogisticsVesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm
  2. 2Acta Marine Christens CSOV Chartered by Vestas
  3. 3New Owner to Continue Operations at German Offshore Wind Farm Previously Set for Decommissioning
  4. 4All Monopiles In at Nordlicht I Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free