Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Jan De Nul Completes Luchterduinen Export Cable Reburial
Operations & Maintenance

October 22, 2021 · about 5 years ago

Jan De Nul Completes Luchterduinen Export Cable Reburial

Jan De Nul’s intertidal trencher Sunfish has reburied a section of the export cable at Eneco’s Luchterduinen offshore wind farm in the Netherlands. For this purpose, Jan De Nul modified its in-house designed and fabricated intertidal trencher Sunfish and reburied the nearshore section of the cable t

2 minutes read
  • LinkedIn
  • X
  • Email
Jan De Nul Completes Luchterduinen Export Cable Reburial
Jan De Nul

Jan De Nul’s intertidal trencher Sunfish has reburied a section of the export cable at Eneco’s Luchterduinen offshore wind farm in the Netherlands.

For this purpose, Jan De Nul modified its in-house designed and fabricated intertidal trencher Sunfish and reburied the nearshore section of the cable to a minimum depth of 2.5 meters below the seabed.

The export cable burial was over the last few years decreasing in depth due to morphological changes, therefore Eneco requested a reburial campaign to guarantee it will at all times remain sufficiently buried and thus protected.

Since the section of decreased burial depth was located in the nearshore zone, it was not accessible with typical offshore trenching vehicles and could not be easily accessed from the beach. Sunfish lowered the nearshore part of the cable working up to 1 kilometer offshore and a water depth of 8.5 meters.

Ernest Diepstraten , project manager at Eneco: “Eneco greatly appreciated working together with Jan De Nul constructively in delivering this project in time and in budget. We are pleased that, thanks to the work of Jan De Nul Group, the cable to our Eneco Luchterduinen wind farm is buried deep enough again so that the wind farm can continue to supply power to our customers.”

Specifically for this project, the Sunfish was modified to a suitable post-lay jet-trenching vehicle with two water pumps delivering each 1250 m³/hr jet water and 3.5-meter long jet swords.

To accurately locate the cable, the vehicle was further equipped with two sets of cable tracker sensors of SMD’s tracking system Artemis using the live tone of the cable. As a result, Eneco did not have to switch off the wind farm during the entire campaign, Jan De Nul stated.

The Luchterduinen offshore wind farm comprises 43 Vestas V112 turbines located approximately 23 kilometers off the coast between Noordwijk and Zandvoort. The 129 MW project was commissioned back in 2015.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Operations & MaintenanceWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Balfour Beatty Wins Contract for Substation to Connect Three Dogger Bank Wind Farms
  2. 2Archer Weighs Sale of Offshore Wind Business After Culzean Project Setbacks
  3. 3Vattenfall Tests New Bird Monitoring Tech at Dutch Offshore Wind Farm
  4. 4IFM Investors to Acquire Majority Stake in UK Port Operator ABP

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free