Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Ports & Logistics›Buss Terminal Sends Off Final Hornsea Two Hardware
Ports & Logistics

October 19, 2021 · about 5 years ago

Buss Terminal Sends Off Final Hornsea Two Hardware

Buss Terminal in Eemshaven, the Netherlands, has completed the handling and load-out of the 165 monopile foundations for the 1,386 MW Hornsea Two offshore wind farm. Over the last 15 months, Eemshaven served as the base port for the handling and load-out of the 165 monopiles and transition pieces. T

1 minutes read
  • LinkedIn
  • X
  • Email
Buss Terminal Sends Off Final Hornsea Two Hardware
Buss Energy Group

Buss Terminal in Eemshaven, the Netherlands, has completed the handling and load-out of the 165 monopile foundations for the 1,386 MW Hornsea Two offshore wind farm.

Over the last 15 months, Eemshaven served as the base port for the handling and load-out of the 165 monopiles and transition pieces.

The Buss Terminal in Eemshaven was contracted by DEME Offshore, responsible for the transport and installation of the winda farm’s foundations.

Related Articles

Contracts & Tenders

DEME Picks Hornsea Two Foundations Base Port

1 min read

Buss Energy Group´s team of project managers, stevedores, and technicians provided a full scope of base harbour activities, including the handling of components of up to 1,230 tonnes per unit, provision of onshore storage solutions for the monopiles and the transition pieces, and provision of warehousing and office facilities.

Furthermore, a custom-designed transition piece gantry handler was used to enable a more efficient logistics and storage set up.

”We are grateful for the exceptional teamwork during the project. Despite the difficulties imposed by the Covid pandemic the installation of foundations was completed ahead of schedule,” John Meijer , Managing Director of Buss Terminal Eemshaven, said.

Located in the North Sea some 89 kilometres off the Yorkshire Coast, UK, Hornsea Two spans an offshore area of 462 square kilometres and will be the world’s largest wind farm when it goes into operation in 2022.

Being developed by Ørsted, the wind farm will comprise 165 Siemens Gamesa 8.4 MW wind turbines, over a hundred of which have already been installed.

Related Articles

Wind Farm Update

100 Turbines Up at Hornsea Two Offshore Wind Farm

1 min read

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Ports & LogisticsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1IFM Investors to Acquire Majority Stake in UK Port Operator ABP
  2. 2TenneT and NKT Jointly Explore Offshore Cable Decommissioning
  3. 3GEOxyz Conducting Seabed Survey at East Anglia Two Offshore Wind Site
  4. 4US Gov’t Seeks New Review of US Wind’s Maryland Project

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free