Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Ørsted Selects CRP Subsea’s Cable Protection System for Borkum Riffgrund 3 and Gode Wind 3
Contracts & Tenders

June 18, 2021 · about 5 years ago

Ørsted Selects CRP Subsea’s Cable Protection System for Borkum Riffgrund 3 and Gode Wind 3

Ørsted has awarded two cable protection system (CPS) contracts to CRP Subsea for the Borkum Riffgrund 3 and Gode Wind 3 offshore wind farms in Germany. CRP Subsea, formerly known as Trelleborg Offshore UK, will supply 223 of its NjordGuard monopile entry cable protection systems for the inter-array

1 minutes read
  • LinkedIn
  • X
  • Email
Ørsted's Borkum Riffgrund 2 offshore wind farm in Germany
Ørsted; Borkum Riffgrund 2

Ørsted has awarded two cable protection system (CPS) contracts to CRP Subsea for the Borkum Riffgrund 3 and Gode Wind 3 offshore wind farms in Germany.

CRP Subsea, formerly known as Trelleborg Offshore UK, will supply 223 of its NjordGuard monopile entry cable protection systems for the inter-array cables on both projects.

The CPS will also protect the cables being used to support the connection between Borkum Riffgrund 3 to the Dolwin Epsilon converter station.

The company said it would start project engineering work immediately, with the production of the 223 CPS systems to take place in its manufacturing facility in the North West of England.

The CPS systems are scheduled to be installed at the two offshore wind farms sites in 2024.

In April, Germany’s Federal Maritime and Hydrographic Agency (BSH) granted planning approval to Ørsted for the 242 MW Gode Wind 3 offshore wind farm, whose construction will be carried out in parallel with the 900 MW Borkum Riffgrund 3 project, which has yet to be approved.

Gode Wind 3 will go into full commercial operation in 2024 and the commissioning of Borkum Riffgrund 3 would follow in 2025. A final investment decision for both projects is still pending.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & Tenders

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1GS Entec Completes Monopile Factory in Korea
  2. 2PGE and Ørsted Add BGB Group to Baltica 2 Offshore Wind Team
  3. 3Fugro Wins UXO Survey Contract for German Offshore Grid Connections
  4. 4Seaway7 Completes Inter-Array Cable Installation at East Anglia Three Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free