Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Final Geotechnical Surveys Wrap Up at Moray West
Wind Farm Update

March 10, 2021 · about 5 years ago

Final Geotechnical Surveys Wrap Up at Moray West

Fugro has completed the final geotechnical survey campaign at the Moray West offshore wind project in the UK. The new data will be combined with survey results from 2019 to finalize the design of the foundations for each turbine location, as well as the two offshore substations. Survey vessel Norman

1 minutes read
  • LinkedIn
  • X
  • Email
Final Geotechnical Surveys Wrap Up at Moray West
Ocean Winds

Fugro has completed the final geotechnical survey campaign at the Moray West offshore wind project in the UK.

The new data will be combined with survey results from 2019 to finalize the design of the foundations for each turbine location, as well as the two offshore substations.

Survey vessel Normand Flower carried out the campaign, with support from Vysus Group, which included cone penetration boreholes to provide full coverage of all foundation locations.

“The survey data is a key part of the design process that will ensure we are ready and able to deliver this significant scale offshore wind project in Scottish waters in line with our programme, and make an important contribution towards Net Zero,” said Project Director for Moray West Adam Morrison .

Moray West will comprise up to 85 turbines installed in the Outer Moray Firth, some 22.5 kilometers southeast of the Caithness coastline. The plan is to have the 850 MW project operational in 2024/25.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1All Monopiles In at Nordlicht I Offshore Wind Farm
  2. 2IWS Fleet Orders Four New Skywalker-Class CSOVs for EUR 260 Million
  3. 3Windward Offshore Officially Names Third CSOV
  4. 4Boskalis to Install Inter-Array Cables at 1 GW Dutch Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free