Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Prep Works for Export Cable Installation to Start at Neart na Gaoithe OWF
Grid Connection

March 8, 2021 · about 5 years ago

Prep Works for Export Cable Installation to Start at Neart na Gaoithe OWF

Preparation works for the export cable installation for the Neart na Gaoithe offshore wind project are expected to commence in mid-March. The area where the activities will take place is the nearshore extent of the wind farm’s export cable corridor. Two jack-up vessels, Capall Mara and C57 Red Squir

2 minutes read
  • LinkedIn
  • X
  • Email
Map illustration of Neart na Gaoithe location
Mainstream Renewable Power; Illustration (archive)

Preparation works for the export cable installation for the Neart na Gaoithe offshore wind project are expected to commence in mid-March. The area where the activities will take place is the nearshore extent of the wind farm’s export cable corridor.

Two jack-up vessels, Capall Mara and C57 Red Squirrel , will carry out a small amount of seabed preparation operations and undertake trenching works along a short section of the nearshore cable route, according to the project’s Notice to Mariners.

The Capall Mara backhoe dredger will work along the two cables routes within the nearshore area, where it will reposition boulders at one of the cable route sections (KP0.65 and KP1.25), and then excavate a trench within which the cable will be laid. Excavated material will be temporarily repositioned to the side of the trench and will be backfilled by Capall Mara once the nearshore cable installation is completed. C57 Red Squirrel will work on the same section of the cable route (KP0.65) to excavate two pits at the existing HDD exits and conduct minor construction works associated with the HDD exit point.

[The article continues below the image.]

Two tugs, Forth Trojan and The Battler will be supporting C57 Red Squirrel jack-up during the operations, while the crew transfer vessel (CTV) Celtic Guardian will transfer personnel between Capall Mara and C57 Red Squirrel and Eyemouth harbour each day. The CTV will also support with periodic minor surveys of the route.

The C57 Red Squirrel jack-up will also be supported by a dive vessel CRC Tempest for the minor HDD construction works, as required.

Onshore construction on Neart na Gaoithe started in November 2019, while offshore construction began in August 2020 with the installation of pile casings.

The 450 MW offshore wind farm, expected to be commissioned in 2023, will comprise 54 Siemens Gamesa 8 MW wind turbines installed on jacket foundations and two GE Renewable Energy Grid Solutions’ offshore substations.

The project, to be built some 15 kilometres off the Fife coast, is owned by EDF Renewables and ESB.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free