Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Scour Protection Works Needed at One Trianel Windpark Borkum Turbine
Operations & Maintenance

May 5, 2020 · about 6 years ago

Scour Protection Works Needed at One Trianel Windpark Borkum Turbine

Trianel Windkraftwerk Borkum has issued a tender for the provision and installation of scour protection at one wind turbine location in the Trianel Windpark Borkum (TWB) offshore wind farm in Germany. The contractor is responsible for the provision of the scour protection material (rocks) and its in

1 minutes read
  • LinkedIn
  • X
  • Email
A photo of Trianel Windpark Borkum in sunset
Trianel-Borkum

Trianel Windkraftwerk Borkum has issued a tender for the provision and installation of scour protection at one wind turbine location in the Trianel Windpark Borkum (TWB) offshore wind farm in Germany.

The contractor is responsible for the provision of the scour protection material (rocks) and its installation. Therefore, the chosen company will also provide any required vessels, equipment, personnel and project execution documentation.

The contract will also cover any port-related handling activities.

Furthermore, the contract further entails pre-, intermediate and as-built surveys to ensure the works have been done according to the installation specifications outlined by TWB.

The deadline for submitting the bids is 15 May 2020.

Scour protection works under this contract will start on 1 August and be completed by the end of this year.

The 200 MW Trianel Windpark Borkum comprises 40 Adwen 5 MW turbines which have been operational since 2015.

The project owner, Trianel Windkraftwerk Borkum, is currently building the project’s second phase, which will feature 32 Senvion 6.2 M152 turbines scheduled to be completed in the first half of this year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Operations & MaintenanceWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Victoria Identifies Preferred Transmission Route for First Offshore Wind Projects
  2. 2China Three Gorges Connects First Qingzhou V & VII Offshore Wind Turbines to Grid
  3. 3Ørsted's First UK Offshore Wind Farm Marks 20 Years of Operation
  4. 4German Offshore Wind Vessel Operator Acquires 50 Pct Stake in Norwegian Crewing Company

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free