Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Fugro Wraps Up First Part of Sofia Investigations
Wind Farm Update

March 20, 2020 · about 6 years ago

Fugro Wraps Up First Part of Sofia Investigations

Fugro has completed the first tranche of offshore site investigations at innogy’s Sofia offshore wind project in the UK. The first tranche is complete with the multi-purpose vessel Fugro Pioneer having finished the geophysical survey of the wind farm’s export cable corridor. According to innogy, the

1 minutes read
  • LinkedIn
  • X
  • Email
Fugro Wraps Up First Part of Sofia Investigations
innogy

Fugro has completed the first tranche of offshore site investigations at innogy’s Sofia offshore wind project in the UK.

The first tranche is complete with the multi-purpose vessel Fugro Pioneer having finished the geophysical survey of the wind farm’s export cable corridor.

According to innogy, the vessel will be back to carry out more survey work later but for now has left the UK after the job.

To remind, the first phase of the six-month offshore site investigations began at the beginning of February .

This includes both geophysical and geotechnical surveys carried out along the route from just off Teesside, between Redcar and Markse-by-the-Sea, to the wind farm site on Dogger Bank in the North Sea.

Sofia , the largest project in innogy’s development portfolio, will comprise up to 200 turbines located 165km off the North East coast on Dogger Bank.

The 1.4GW offshore wind farm is expected to enter the onshore construction phase in 2021, with commissioning scheduled for 2026.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free