Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›R&D›KPMG: Nearshore Wind Farms Cost-Cutters for Danish Industry
R&D

October 9, 2019 · about 7 years ago

KPMG: Nearshore Wind Farms Cost-Cutters for Danish Industry

Developing nearshore wind farms brings significant savings to the community compared to offshore wind projects located more than 20km from the coast, according to an analysis done by KPMG for the Danish HOFOR and European Energy A/S. According to the study, nearshore wind farms can help Denmark achi

2 minutes read
  • LinkedIn
  • X
  • Email

Developing nearshore wind farms brings significant savings to the community compared to offshore wind projects located more than 20km from the coast, according to an analysis done by KPMG for the Danish HOFOR and European Energy A/S.

According to the study, nearshore wind farms can help Denmark achieve a reduction of CO2 emissions by 70% by 2030 in a cost-effective manner.

The analysis, which sets out a number of scenarios where the upcoming 1GW Thor offshore wind farm is compared with five nearshore wind farms with a total corresponding capacity, shows a socio-economic gain of 2-14% for the combined nearshore wind farms when compared to the Thor project.

In particular, the development of nearshore wind farms is cheaper because of the shorter distance to the shore and lower water depth, as well as the connection to the electricity grid.

Additionally, local residents can become co-owners of turbines that are within 16km of the coast due to the purchase right scheme.

“From this analysis, it is reasonable from a socio-economic point of view, to establish nearshore wind as part of the Danish energy mix. The green transformation of our energy sector is a gigantic task that requires extremely large investments. Coastal sea wind can contribute to reducing the cost of future Danish offshore wind turbine capacity by billions,” said Jan Kauffmann , Director of Economics and Business at HOFOR.

The report also concludes that a setup of several smaller nearshore wind projects would increase the security of supply, as a breakdown of a cable connection to land will affect only one of the wind farms, as opposed to a large offshore wind farm where cable breakdowns can stop the supply of all electricity.

European Energy and HOFOR emphasize that it is obvious for Denmark to exploit the favorable wind conditions in the North Sea, but the country cannot count only on offshore wind to create the entire green transition as solar, onshore wind, nearshore wind farms and biogas have a natural place in the energy mix.

Last year, the Danish parliament unanimously voted for a new energy agreement which includes building three new offshore wind projects, the first of which is Thor, by 2030 with a total capacity of at least 2.4GW.

The up to 1GW wind farm will feature turbines with an individual capacity of between 13MW and 15MW and is expected to be commissioned between 2024 and 2027.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

R&D

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fugro Completes 2026 Survey Campaign for Ireland’s 900 MW Offshore Wind Project
  2. 2Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection
  3. 3All Turbines Installed and Generating Power at Taiwan’s 1 GW Offshore Wind Farm
  4. 4Canada Pledges CAD 100 Million to Advance Nova Scotia’s Offshore Wind

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free