Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›TenneT Seeks Non-UXO Survey Squad
Contracts & Tenders

September 20, 2019 · about 7 years ago

TenneT Seeks Non-UXO Survey Squad

TenneT TSO has issued a tender seeking non-UXO offshore route survey services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. The tender covers the 700MW Hollandse Kust (west) Beta, the 700MW Ten noorden van de Waddeneilanden, the 2GW IJmuiden Ver Alpha, an

1 minutes read
  • LinkedIn
  • X
  • Email

TenneT TSO has issued a tender seeking non-UXO offshore route survey services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030.

The tender covers the 700MW Hollandse Kust (west) Beta, the 700MW Ten noorden van de Waddeneilanden, the 2GW IJmuiden Ver Alpha, and the 2GW IJmuiden Ver Beta offshore wind farm zones.

The Offshore Wind Energy Roadmap 2030 also includes the Hollandse Kust (west) Alpha area which is not part of the tender.

TenneT is in charge of the engineering, procurement, installation, construction, and operation of the connections between the future offshore wind farms, through converter platforms, to the onshore network.

The contract is expected to begin on 1 April 2020 and have a duration until the same date in 2030. The deadline for submitting applications is 16 October.

The Offshore Wind Energy Roadmap 2030 sets out plans for the development of additional 7GW of offshore wind capacity in the Dutch North Sea between 2024 and 2030. Tenders for the new wind farm zones will be opened from 2021 onward, starting with the Holland Kust (west).

Recently, TenneT issued a tender seeking UXO consultancy services for the Dutch offshore wind farm zones.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & Tenders

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Acciona Selected for Victoria’s 2 GW Offshore Wind Transmission Project
  2. 2Trump Administration Seeks Remand of COP Approval for Offshore Wind Farm Now in Final Commissioning Stage
  3. 3Ofgem to Launch Record Tender as UK Regulator Seeks Owner of Hornsea 3 Offshore Transmission Assets
  4. 4French Engineering Company Acquires Irish Sea Contractors to Expand Offshore Wind and Cable Services

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free