offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Van Oord to Install Changhua 1 and 2a Cables
Contracts & Tenders

September 18, 2019 · about 7 years ago

Van Oord to Install Changhua 1 and 2a Cables

Van Oord has been awarded the contract by Ørsted for the cable installation works at the Greater Changhua 1 & 2a offshore wind farms in Taiwan. The wind farms have a capacity of 900MW and are located between 35 and 60 kilometres off the west coast of Changhua County. Van Oord is responsible for the

1 minutes read
  • LinkedIn
  • X
  • Email

Van Oord has been awarded the contract by Ørsted for the cable installation works at the Greater Changhua 1 & 2a offshore wind farms in Taiwan.

The wind farms have a capacity of 900MW and are located between 35 and 60 kilometres off the west coast of Changhua County.

Van Oord is responsible for the transportation, installation, and burial of the 111 inter-array cables, with a total length of approximately 135 kilometres, and the three export cables, with a total of approximately 145 kilometres.

To carry out the work, Van Oord will deploy its dedicated cable-laying vessel Nexus, equipped with a cable carousel with a capacity of 5,000 tonnes. Van Oord’s own trencher Dig-It will bury the cables to the required depth. The installation work starts in 2021.

The Greater Changhua 1 & 2a offshore wind farms will be the first cable project in Taiwan for Van Oord. The wind farms will comprise 111 Siemens Gamesa 8MW wind turbines installed on jacket foundations. The offshore wind farms will be constructed in 2021 and 2022.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Contracts & TendersWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Young Oysters Deployed on Two North Sea Cable Crossings
  2. 2Pacifico Energy Unveils EUR 860+ Million Investment in Two Offshore Wind Projects in South Korea
  3. 3Fourth Vard-Built CSOV Joins Windward Offshore Fleet
  4. 4ABS to Support Japanese Company’s 18 MW Floating Wind Turbine Pilot in Brazil

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free