First TWBII Turbine Parts Embark on Taillevent

Jan De Nul’s offshore installation vessel Taillevent has begun loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII offshore wind farm will comprise 32 Senvion 6.2M152 turbines installed at the project site some 40km north of the island

1 minutes read

Jan De Nul’s offshore installation vessel Taillevent has begun loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm.

The 200MW TWBII offshore wind farm will comprise 32 Senvion 6.2M152 turbines installed at the project site some 40km north of the island of Borkum in Germany.

Taillevent loaded the first three towers, blades and nacelles at the Buss Terminal Eemshaven, Senvion’s base for the project.

To remind, turbine installation was initially scheduled to start mid-April but was postponed until summer after Senvion had filed for self-administration .

By then, 15 turbines had been delivered and transported to the base port in Eemshave. The remaining 17 units are expected to be delivered this autumn.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.