Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Marine Coordination Services Scores Norther Contract
Contracts & Tenders

January 23, 2019 · about 7 years ago

Marine Coordination Services Scores Norther Contract

Van Oord has contracted Marine Coordination Services to provide a team to support the construction of the Norther offshore wind farm in Belgium. Under the contract, Marine Coordination Services is currently deploying a team of four professionals to support the marine coordination center. According t

1 minutes read
  • LinkedIn
  • X
  • Email

Van Oord has contracted Marine Coordination Services to provide a team to support the construction of the Norther offshore wind farm in Belgium.

Under the contract, Marine Coordination Services is currently deploying a team of four professionals to support the marine coordination center.

According to the Dutch company, the team, which can be deployed 24/7, will operate from Ostend.

As the Balance of Plant contractor, Van Oord is responsible for the engineering, procurement, supply and installation of turbine foundations, the Offshore High Voltage Station (OHVS), inter-array and export cables, as well as the installation of turbines.

Offshore works began in May with the installation of scour protection at the project site some 23km off the port of Zeebrugge. Van Oord’s vessel Aeolus started installing the monopile foundations in August, the same month in which the OHVS was installed .

The Norther offshore wind farm will comprise a total of 44 MHI Vestas V164-8.0 MW turbines optimized to deliver a maximum output of 8.4MW. The project is expected to be operational in the third quarter of the year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & Tenders

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Offshore Charging, Rare Earth Magnet Projects Secure EU Funding
  2. 2Terna Energy Plans 45 MW Floating Wind Pilot in Greece
  3. 3Kumagai Gumi Joins DemoSATH as Floating Wind Test Project Extended Through 2027
  4. 4New Zealand Opens First Offshore Wind Feasibility Permit Round

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free