offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›Planning Inspectorate Schedules Hornsea Three DCO Meets
Authorities

January 9, 2019 · about 7 years ago

Planning Inspectorate Schedules Hornsea Three DCO Meets

The UK Planning Inspectorate is holding hearings and accompanied site inspections for the Hornsea Project Three offshore wind farm as part of its examination of Ørsted’s application for an order granting development consent. The first hearing will take place on 28 January at 7:00 p.m. local time at

1 minutes read
  • LinkedIn
  • X
  • Email

The UK Planning Inspectorate is holding hearings and accompanied site inspections for the Hornsea Project Three offshore wind farm as part of its examination of Ørsted’s application for an order granting development consent.

The first hearing will take place on 28 January at 7:00 p.m. local time at the North Norfolk District Council.

The next three meetings are scheduled for 29, 30 and 31 January in the presidential suite of the Mercure Norwich Hotel and will begin at 9:30 a.m.

In case all agenda items are not adequately covered on 31 January, a compulsory acquisition hearing will be held on 1 February.

Further to the procedural decision and timetable, accompanied site inspections are planned to commence on 28 January at 9:30 a.m. at the car park of Lakenham Hewett RFC.

Additional inspections will be held on 5 March and will cover locations in the northern part of the onshore cable route and the proposed main construction compound.

Ørsted is proposing to build up to 300 turbines at the 2.4GW Hornsea Project Three offshore wind farm more than 120km off the north Norfolk coast.

If the development consent order application is successful, the project is expected to enter the construction phase in 2020 at the earliest.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

AuthoritiesBusiness & Finance

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Gennaker Offshore Wind Farm Reaches Financial Close
  2. 2Half of Turbines at Dieppe–Le Tréport Offshore Wind Farm In Place
  3. 3Gondan Launches Østensjø Rederi's Ocean Energy Support Vessel
  4. 4New Boskalis Rock Installation Vessel Starts Work Offshore Poland

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free