Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Environment›Hornsea Project Three Continues the Norfolk Tour
Environment

June 23, 2017 · about 9 years ago

Hornsea Project Three Continues the Norfolk Tour

DONG Energy plans to publish and formally consult on the Preliminary Environmental Information Report (PEIR) for the proposed 2.4GW Hornsea Project Three offshore wind project over the summer.

1 minutes read
  • LinkedIn
  • X
  • Email

DONG Energy plans to publish and formally consult on the Preliminary Environmental Information Report (PEIR) for the proposed 2.4GW Hornsea Project Three offshore wind project over the summer.

The PEIR will present the findings of initial surveys and assessments and will enable consultees to develop an informed view of the potential environmental effects of the project, DONG said.

In March 2017, DONG held a second round of community consultation events for the Hornsea Project Three development in targeted locations along the proposed onshore cable route and within the onshore High Voltage Alternating Current (HVAC) booster station and onshore substation search areas in Norfolk.

This round of events, Phase 1.B, was introduced following refinement of the original search area to an indicative preferred export cable corridor.

Further community consultation events will be held in September 2017 to consult and seek feedback on these proposals.

DONG is proposing to develop the Hornsea Project Three offshore wind farm over 120 km off the north Norfolk coast.

As a Nationally Significant Infrastructure Project (NSIP), Hornsea Project Three must apply for a Development Consent Order (DCO) and be granted consent by the UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) before it can be built.

Prior to submitting a DCO application, DONG must carry out pre-application consultation with members of the local community, as well as landowners and statutory bodies, on the proposed development.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

EnvironmentGrid ConnectionR&DWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1ScottishPower Renewables Completes ‘Record-Breaking’ Cable Landfall Operation for East Anglia Two
  2. 2Bidding Period Closes for 10 GW French Offshore Wind Tender
  3. 3DEME to Install Wind Turbines at Vattenfall and CIP’s 1 GW Dutch Offshore Wind Farm
  4. 4Acciona Selected for Victoria’s 2 GW Offshore Wind Transmission Project

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free