Advertisement

Grid Connection

about 9 years ago

Oleg Strashnov Installs Walney Extension Substations

Seaway Heavy Lifting’s vessel Oleg Strashnov has installed two offshore substations on DONG Energy’s 660MW Walney Extension wind farm in the Irish Sea.

1 minutes read

Seaway Heavy Lifting’s vessel Oleg Strashnov has installed two offshore substations on DONG Energy’s 660MW Walney Extension wind farm in the Irish Sea.

The two 2,900-tonne substations, comprising topsides and jacket foundations, were built by a consortium of Engie Fabricom and Iemants and were shipped out from Hoboken, Belgium, in March.

Located next to the 367.2MW Walney 1 & 2 offshore wind farms off Cumbria, Walney Extension will be the largest wind farm in the world when built and commissioned in 2019.

The wind farm will consist of 40 8MW MHI Vestas and 47 7MW Siemens wind turbines.

Photos: Seaway Heavy Lifting

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.