Bladt Gets Busy with Hornsea One Substations

Prefabrication work on three substations for DONG Energy’s 1.2GW Hornsea Project One offshore wind farm is well under way, Danish offshore structure construction specialist Bladt Industries reports. Each substation will weigh 2,800 tons and the first unit will be delivered during the first half of 2

1 minutes read

Prefabrication work on three substations for DONG Energy’s 1.2GW Hornsea Project One offshore wind farm is well under way, Danish offshore structure construction specialist Bladt Industries reports.

Each substation will weigh 2,800 tons and the first unit will be delivered during the first half of 2018, the company said.

The contract represents Bladt’s first ever order to fabricate three substations at the same time for one project as serial production.

The electrical work for the substations is sub-contracted to Bladt’s long-term partner Semco Maritime.

DONG ordered the three substations in May 2016.

The Hornsea Project One offshore wind farm will comprise 174 wind turbines and four substations.

Advertisement

The offshore wind farm will be situated in the North Sea, 120 kilometres off the coast of Yorkshire in the UK.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.