Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›National Grid Progressing with BIWF Cabling Works
Wind Farm Update

July 22, 2016 · about 10 years ago

National Grid Progressing with BIWF Cabling Works

National Grid, which will build, own and operate the majority of the new electrical infrastructure needed to connect the Block Island Wind Farm to the electric grid on Block Island and mainland Rhode Island, is progressing with cabling works required to connect the first American offshore wind farm

2 minutes read
  • LinkedIn
  • X
  • Email

National Grid, which will build, own and operate the majority of the new electrical infrastructure needed to connect the Block Island Wind Farm to the electric grid on Block Island and mainland Rhode Island, is progressing with cabling works required to connect the first American offshore wind farm to land.

In Narragansett, Rhode Island, all of the manholes and duct bank have been installed and crews have finished pulling all of the cable through the conduits along Burnside Avenue and Route 108. The only cable pulling work that remains is at the connection with the substations, which will take place in the fall.

Work continues on the new substation at Dillon’s Corner and at the Wakefield Substation. National Grid is preparing to install a sound mitigation barrier around the perimeter of the substation to reduce the noise from construction activities.

Both submarine cables, including export cable to wind farm and cable from mainland RI, have made landfall on Block Island, and the interconnection with the land cable has been completed.

The land cable installation is nearing completion and civil and foundation work for the new National Grid substation on BIPCo property continues.

Meanwhile, Deepwater Wind, the wind farm developer, is gearing up for turbine installation.

Fred. Olsen Windcarrier’s vessel Brave Tern recently arrived to St. Nazaire in France to pick up nacelles for the turbine installation works scheduled to start at the beginning of August.

Fred. Olsen-related company Global Wind Service (GWS) is in charge of lift supervision and installation of the GE Renewable Energy’s Haliade 150-6MW wind turbines.

The 240-foot long turbine blades have already arrived at Deepwater Wind and GE’s assembly facility at Port of Providence. The blades and the tower sections , already assembled there, are scheduled to travel by boat to the Block Island Wind Farm site in the beginning of August.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fugro Completes 2026 Survey Campaign for Ireland’s 900 MW Offshore Wind Project
  2. 2Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection
  3. 3All Turbines Installed and Generating Power at Taiwan’s 1 GW Offshore Wind Farm
  4. 4Canada Pledges CAD 100 Million to Advance Nova Scotia’s Offshore Wind

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free