offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Dragados Offshore Cracks Offshore Wind Market with Hornsea Project 1 Jackets
Business & Finance

June 10, 2016 · about 10 years ago

Dragados Offshore Cracks Offshore Wind Market with Hornsea Project 1 Jackets

DONG Energy has awarded Dragados Offshore, a Spanish engineering, procurement, and construction (EPC) contractor and a part of the ACS Group, with a contract to deliver four substation jackets for the 1.2GW Hornsea Project One offshore wind farm in the UK. The scope of work awarded to Dragados Offsh

1 minutes read
  • LinkedIn
  • X
  • Email

DONG Energy has awarded Dragados Offshore, a Spanish engineering, procurement, and construction (EPC) contractor and a part of the ACS Group, with a contract to deliver four substation jackets for the 1.2GW Hornsea Project One offshore wind farm in the UK.

The scope of work awarded to Dragados Offshore is the procurement and fabrication of the jackets and piles of three offshore substations and a reactive compensation substation (RCS). Dragados Offshore will initiate the project immediately, and delivery of the jackets is scheduled for early 2018.

The contract is considered a major milestone as it initiates Dragados Offshore activities into the offshore wind industry.

Hornsea Project One will be located approximately 120 kilometres off the Yorkshire coast and will cover approximately 407 square kilometers. Once completed it will be the world’s biggest offshore wind farm.

The project consists of 174 Siemens 7MW wind turbines, connected to three offshore collector substations and the RCS, the latter one located between the offshore wind farm and the shore.

The offshore collector substations transfer power from the incoming wind turbines’ medium voltage cables to high voltage, exporting it via the RCS onto the National Grid. The purpose of the RCS is to compensate for the reactive power generated in the wind farm power system.

DONG reached the Final Investment Decision to build the wind farm in February 2016.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Business & FinanceGrid ConnectionWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1ABS to Support Japanese Company’s 18 MW Floating Wind Turbine Pilot in Brazil
  2. 2Equinor to Deploy Cable Monitoring Tech at 9-Year-Old Offshore Wind Farm
  3. 3All Foundations In Place at Bałtyk 2 & 3
  4. 4OWC-Led Consortium to Perform Feasibility Study for Morocco’s First Offshore Wind Farm

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free