Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Hollandia Offshore Pens Kriegers Flak Substations Fabrication Contract
Business & Finance

June 3, 2016 · about 10 years ago

Hollandia Offshore Pens Kriegers Flak Substations Fabrication Contract

Hollandia Offshore B.V. and the Danish transmission system operator, Energinet.dk, signed a contract for the engineering, procurement and commissioning of the Kriegers Flak substations on 31 May. The project comprises two unmanned substations which are due for delivery to the installation site in Ap

2 minutes read
  • LinkedIn
  • X
  • Email

Hollandia Offshore B.V. and the Danish transmission system operator, Energinet.dk, signed a contract for the engineering, procurement and commissioning of the Kriegers Flak substations on 31 May.

The project comprises two unmanned substations which are due for delivery to the installation site in April 2018. Commissioning will take place in April and May of 2018.

The Kriegers Flak substations will be installed in the Danish sector of the Baltic Sea. The wind farm consists of 2 sections, each with its own substation.

The west section, Kriegers Flak A, will have a total capacity of 200MW. The east section, Kriegers Flak B, will have a total capacity of 400MW. The Kriegers Flak B substation will also serve as the support for the KFE module which is part of the so called Combined Grid Solution project which is run by Energinet.dk and the German transmission systems operator 50 Hertz. The Combined Grid Solution project is funded with up to EUR 150 million from the European Energy Programme for Recovery.

The scope of works includes transport to the offshore site and commissioning. Hollandia Offshore will undertake the work together with Croonwolter&dros who will be responsible for the design, procurement and installation of the utility systems such as the low voltage systems, the fire fighting systems and the HVAC.

The project will be executed at the yard of Hollandia Offshore in Krimpen aan den IJssel. Most of the fabrication will take place in a controlled workshop environment in one of the recently built fabrication shops.

Nico Noorlander, Managing Director of Hollandia Offshore, said: “We are very pleased that we have been awarded this challenging contract for the Kriegers Flak substations. We are confident that we are able to continue the excellent working relationship with our client Energinet.dk for which we recently delivered the jacket for the Horns Rev C substation.”

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceGrid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Wood Thilsted Secures New Contract on Outer Dowsing Offshore Wind Farm
  2. 2Vattenfall to Offer 200 MW of Balancing Power from German Offshore Wind Farm
  3. 3Fugro Completes 2026 Survey Campaign for Ireland’s 900 MW Offshore Wind Project
  4. 4Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free