Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Vessels›First Veja Mate Monopiles Reach Eemshaven
Vessels

March 14, 2016 · about 10 years ago

First Veja Mate Monopiles Reach Eemshaven

The first three super-sized monopiles built for the 402MW Veja Mate offshore wind farm arrived at the Dutch Eemshaven seaport on 10 March, with the remaining 64 giants soon to follow, Eemshavenonline.nl reports The monopiles were constructed in Rostock, Germany, by EEW Special Pipe Constructions Gmb

1 minutes read
  • LinkedIn
  • X
  • Email

The first three super-sized monopiles built for the 402MW Veja Mate offshore wind farm arrived at the Dutch Eemshaven seaport on 10 March, with the remaining 64 giants soon to follow, Eemshavenonline.nl reports

The monopiles were constructed in Rostock, Germany, by EEW Special Pipe Constructions GmbH. Weighing 1,302.5 tons each, they are the world’s heaviest monopiles ever built. The first monopile was rolled out of the factory in Rostock on 2 March. EEW expects to complete the construction of all 67 monopiles by the end of June.

The handover of the first monopile to Offshore Windforce, a joint venture of Boskalis and Volker Stevin International, is scheduled for the end of April 2016.

Offshore Windforce will then be in charge of loading and transport. The first monopiles are expected to be installed at the site in the following few months. They will be transported from Eemshaven, the base port for the project, by Seajacks Scylla, the world’s largest wind turbine installation vessel.

Veja Mate, located 95 km northwest from the island of Borkum in the German North Sea, will comprise 67 6MW Siemens turbines. Once fully operational in 2018, the wind farm will produce enough power to meet the demand of around 400,000 German households.

Offshore WIND Staff

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

VesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Offshore Charging, Rare Earth Magnet Projects Secure EU Funding
  2. 2Terna Energy Plans 45 MW Floating Wind Pilot in Greece
  3. 3Kumagai Gumi Joins DemoSATH as Floating Wind Test Project Extended Through 2027
  4. 4New Zealand Opens First Offshore Wind Feasibility Permit Round

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free