All 150 Gemini Foundations in Place

The last of 150 foundations at the Gemini offshore wind farm was installed on 17 October. On 1 July, Van Oord’s installation vessel Aeolus, together with Swire Blue Ocean’s Pacific Osprey, started the installation and completed the work one month earlier than scheduled. On 1 February 2016, both vess

1 minutes read

The last of 150 foundations at the Gemini offshore wind farm was installed on 17 October.

On 1 July, Van Oord’s installation vessel Aeolus , together with Swire Blue Ocean’s Pacific Osprey , started the installation and completed the work one month earlier than scheduled.

On 1 February 2016, both vessels will return to the project, completely modified for the installation of the 150 wind turbines. They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini offshore wind farm.

Image: Van Oord

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.