Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›BWS Backs Van Oord’s Foundation Work
News

October 8, 2015 · about 11 years ago

BWS Backs Van Oord’s Foundation Work

Blue Water Shipping (BWS) is transporting 76 wind turbine foundations for Van Oord Offshore Wind Projects for the Gemini Offshore Wind Park. “Our own naval architect has together with the shipping line come up with a change in construction of the chartered vessel so that it can accommodate the found

1 minutes read
  • LinkedIn
  • X
  • Email

Blue Water Shipping (BWS) is transporting 76 wind turbine foundations for Van Oord Offshore Wind Projects for the Gemini Offshore Wind Park.

“Our own naval architect has together with the shipping line come up with a change in construction of the chartered vessel so that it can accommodate the foundations. After ten days’ dry-docking in Sweden, the ship was ready for the first shipment,” said Brian Sørensen, Sales Manager for Blue Water’s Wind Logistics.

Focus has been to minimise the clients’ total costs for the transport. That is why the foundations are being transported on a vessel instead of a barge. This is often a cheaper solution and is also less sensitive to bad weather.

“Our clients have a lot at stake, so it is important that we deliver on time. All the installation vessels to which we deliver foundations must be kept occupied as waiting time is too costly,” said Brian Sørensen .

The vessel will make a total of 38 trips carrying two foundations at a time. Most of the foundations will be transported from the German city of Rostock, but there are also a few shipments from Flushing in Holland.

Van Oord Offshore Wind Projects will be handling the installation of the foundations, the electric infrastructure, cables, transformer stations and is also responsible for installation of the turbines, which will be performed by the installation vessel Aeolus .

Image: Blue Water Shipping

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

News

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fugro Completes 2026 Survey Campaign for Ireland’s 900 MW Offshore Wind Project
  2. 2Nexans Starts Manufacturing 525 kV Subsea Cables for LanWin2 Offshore Wind Grid Connection
  3. 3All Turbines Installed and Generating Power at Taiwan’s 1 GW Offshore Wind Farm
  4. 4Canada Pledges CAD 100 Million to Advance Nova Scotia’s Offshore Wind

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free