Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Carnegie Demonstrates CETO Units Swap
Operations & Maintenance

September 8, 2015 · about 11 years ago

Carnegie Demonstrates CETO Units Swap

Carnegie Wave Energy has demonstrated the ability to swap CETO units during plant operation by retrieving the second CETO 5 unit and deploying CETO unit #1 in its place last week. The retrieval of the second CETO 5 unit was informed by lessons learnt during the retrieval of the first CETO 5 unit ear

2 minutes read
  • LinkedIn
  • X
  • Email

Carnegie Wave Energy has demonstrated the ability to swap CETO units during plant operation by retrieving the second CETO 5 unit and deploying CETO unit #1 in its place last week.

The retrieval of the second CETO 5 unit was informed by lessons learnt during the retrieval of the first CETO 5 unit earlier this year. As with the first unit, CETO 5 unit #2 was retrieved on its first attempt by disconnecting the unit from the seabed foundation, using the hydraulic “quick connect” technology.

CETO 5 unit #1, which had been inspected and overhauled over the past months, was then installed in the former position of unit #2.

This operation was deliberately carried out in the higher sea state conditions that tend to prevail off the Western Australian coast between July and September. It demonstrates the ease at which the CETO system can be installed and retrieved and its interchangeability across multiple unit locations. Both of these factors are important for future operation and maintenance activities, Carnegie said.

Carnegie Chief Operating Officer, Greg Allen , said: “The successful retrieval of the CETO units after record breaking operational hours has validated Carnegie’s installation and retrieval methodology. We have shown that our units are able to survive and operate over a sustained period of time in a variety of weather conditions, addressing the key industry challenges of survivability and reliability.”

Carnegie has now successfully retrieved two out of its three installed units, as well as redeployed the first unit. The redeployed CETO 5 unit #1 is now in a final, post-winter data collection campaign.

The learnings from these operation and maintenance activities are being fed into the design phase for the CETO 6 Project at Garden Island.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Operations & MaintenanceTechnology

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Terna Energy Plans 45 MW Floating Wind Pilot in Greece
  2. 2Kumagai Gumi Joins DemoSATH as Floating Wind Test Project Extended Through 2027
  3. 3New Zealand Opens First Offshore Wind Feasibility Permit Round
  4. 4SSE Taps Seaway7 for Berwick Bank B Foundations, Inter-Array Cables

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free