Advertisement

Wind Farm Update

about 11 years ago

Gode Wind Foundation in Water

The first foundation was successfully installed at the Gode Wind Offshore Wind Farm in the German North Sea yesterday. With this project, DONG Energy is building Germany’s biggest offshore wind farm 45km from the mainland and around 33km from the islands Juist and Norderney. Trine Borum Bojsen, Mana

1 minutes read

The first foundation was successfully installed at the Gode Wind Offshore Wind Farm in the German North Sea yesterday.

With this project, DONG Energy is building Germany’s biggest offshore wind farm 45km from the mainland and around 33km from the islands Juist and Norderney.

Trine Borum Bojsen , Managing Director from DONG Energy in Germany said: “It’s extremely satisfying to see that Gode Wind’s first foundation has been installed. This is not only a milestone for DONG Energy and a step closer to our goal of installing 6.5GW by 2020; it’s also a milestone for Germany in pushing forward the energy transition.”

The monopile, which is 67m long and has a weight of 939 tonnes, is the biggest and heaviest monopile which has ever been installed in the German part of the North Sea.

In total 97 foundations, with diameter of 7.5m will be installed in approximately 33 meters water depth. Gode Wind Offshore Wind Farm is the largest single investment ever made by DONG Energy and once completed, it will be the largest offshore wind farm in Germany.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.