Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›French Towing Company Backs Fecamp OWF Project
Business & Finance

February 26, 2015 · about 11 years ago

French Towing Company Backs Fecamp OWF Project

On February 9th 2015, the first Seatower gravity based foundation (GBS) for the Fecamp offshore wind farm was successfully installed 15km off the coast of Normandy. During the course of this project, towage specialist BOLUDA FRANCE provided its expertise, procurement and towage services to contribut

1 minutes read
  • LinkedIn
  • X
  • Email

On February 9th 2015, the first Seatower gravity based foundation (GBS) for the Fecamp offshore wind farm was successfully installed 15km off the coast of Normandy.

During the course of this project, towage specialist BOLUDA FRANCE provided its expertise, procurement and towage services to contribute to the installation of the very first offshore wind structure in French waters.

Denis Monserand, CEO of BOLUDA FRANCE said : “The installation of the Fecamp met mast represents a milestone in the French offshore wind market. We are proud to have carried out this operation and to be the first towage company to tow a Seatower gravity based foundation.

“This will undoubtedly affirm our expertise and confirm our ambition on the European offshore wind market .”

Three offshore tugs from BOLUDA FRANCE’s fleet were mobilized. The scope of work was harbour towage, ocean towage, and positioning.

The tugs recovered the towing pennants from the GBS at Le Havre. The convoy managed the critical and sensitive passage of the harbour locks.

Once at sea, all three tugs worked in coordination to minimize the inclination during the tow of the 1800 tons and 50-meter high structure. At the installation site, the convoy hooked the GBS onto pre-laid anchors and then lowered it and smoothly installed within the target box area.

Images: BOLUDA FRANCE/Jeune Marine

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceVesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm
  2. 2Acta Marine Christens CSOV Chartered by Vestas
  3. 3New Owner to Continue Operations at German Offshore Wind Farm Previously Set for Decommissioning
  4. 4All Monopiles In at Nordlicht I Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free