Advertisement

Wind Farm Update

about 11 years ago

Siemens Prepares Base for Westermeerwind Construction

Siemens has decided to make Urk a base port for the management of Westermeerwind nearshore wind farm construction. The company has already installed temporary offices, installed cranes and built a storage area in the harbour, according to the Dutch media. Urk port will be used primarily to transport

1 minutes read

Siemens has decided to make Urk a base port for the management of Westermeerwind nearshore wind farm construction.

The company has already installed temporary offices, installed cranes and built a storage area in the harbour, according to the Dutch media.

Urk port will be used primarily to transport people and smaller parts to the construction site, while larger components will be transported from the Port of Vlissingen, Amsterdam and the working harbour Oude Zeug.

Siemens plans to erect 48 Siemens 3MW turbines in three rows 500 metres and 1100 metres from the dikes of the Noordoostpolder.

The construction of the 144MW wind farm is expected to be completed by the end of this year or in early 2016.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.