Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›Dogger Bank Creyke Beck’s Examination Complete
News

August 18, 2014 · about 12 years ago

Dogger Bank Creyke Beck’s Examination Complete

The six-month examination of the Dogger Bank Creyke Beck development consent order application by the Planning Inspectorate concludes today (August 18). The examination started in February this year and included one open floor public hearing and an additional nine days of issue-specific hearings plu

1 minutes read
  • LinkedIn
  • X
  • Email

The six-month examination of the Dogger Bank Creyke Beck development consent order application by the Planning Inspectorate concludes today (August 18).

The examination started in February this year and included one open floor public hearing and an additional nine days of issue-specific hearings plus two site visits to the proposed landfall and onshore cable route.

The examination involved more than 30 stakeholder organisations and individuals with an interest in the project proposals and a total of more than 500 documents were submitted as part of the process.

Dogger Bank Creyke Beck consent manager Melissa Read said it was an open and thorough process with full involvement of stakeholders and interested parties.

“Forewind worked hard to agree nearly 100 statements of common ground with key stakeholders, ranging from environmental and technical organisations to local parish councils,” she said.

The examiners will now spend up to three months preparing a recommendation for the Secretary of State for Energy and Climate Change, who will take a further three months to issue the consenting decision including, if approved, the final development consent order.

It is anticipated that the Secretary of State’s decision will be announced in February 2015.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

News

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Norway Revises Utsira Nord Floating Wind Support Terms
  2. 2Germany to Auction 4 GW of Offshore Wind Capacity in 2027 Under Revised Site Plan
  3. 3Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  4. 4US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free