offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Ballast Nedam Completes Monopile Installation at Butendiek
Wind Farm Update

July 22, 2014 · about 12 years ago

Ballast Nedam Completes Monopile Installation at Butendiek

Today, Tuesday 22nd July 2014, Ballast Nedam Offshore installed the 80th and last monopile at the Butendiek Offshore Wind Farm in the German sector of the North Sea. The installation of all these monopiles was completed well within four-month time. This exceptional achievement is entirely due to the

2 minutes read
  • LinkedIn
  • X
  • Email

Today, Tuesday 22nd July 2014, Ballast Nedam Offshore installed the 80th and last monopile at the Butendiek Offshore Wind Farm in the German sector of the North Sea.

The installation of all these monopiles was completed well within four-month time. This exceptional achievement is entirely due to the efforts of a dedicated and professional team, working both at Ballast Nedam and at WPD.

The actual installation work was performed by the HLV Svanen. In a highly efficient operation, a continuous stream of floating monopiles was transported from Esbjerg to the offshore site.

WPD’s Butendiek Offshore Wind Farm is located in the German Bight, 32 kilometres west of the German island of Sylt. The depth of the sea at the Butendiek Offshore Wind Farm ranges from 17 to 22 metres. The wind farm itself consists of 80 turbines, each with a capacity of 3.6 MW (288 MW in total).

The monopile installation work at the Butendiek Offshore Wind Farm is just part of the total EPCI foundation package that was contracted out to Ballast Nedam. All operations to date, including the design, certification and fabrication of the foundations, as well as the installation of monopiles, have met the agreed deadlines.

The design work was completed in-house by Ballast Nedam Engineering. All aspects of fabrication and logistics management were handled by Ballast Nedam Offshore, including the highly effective feeding method involving the use of offshore loadouts. Work on the transition pieces is proceeding as planned, and almost 50% of them have now been installed.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Wind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1TetraSpar Floater Completes Five-Year Testing Campaign Offshore Norway
  2. 2Standardization and Industrialization Could Cut Offshore Wind Costs in North Sea by 28% - Study
  3. 3Industrialisation, Productivity and Global Competition: What's Next for Blade Manufacturing?
  4. 4Massachusetts Invests USD 4.2 Million to Boost Offshore Wind Workforce and Research

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free