offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Seafox 5 Finishes DanTysk Foundation Installation (Germany)
Operations & Maintenance

December 16, 2013 · about 12 years ago

Seafox 5 Finishes DanTysk Foundation Installation (Germany)

As announced on December 13, all of the 80 foundations for the DanTysk offshore wind farm are now installed. This was achieved by using the largest self-propelled installation jack-up vessel of the Workfox fleet, the Seafox 5. The vessel successfully completed the installation of 80 monopiles and tr

1 minutes read
  • LinkedIn
  • X
  • Email

As announced on December 13, all of the 80 foundations for the DanTysk offshore wind farm are now installed.

This was achieved by using the largest self-propelled installation jack-up vessel of the Workfox fleet, the Seafox 5. The vessel successfully completed the installation of 80 monopiles and transition pieces for the DanTysk offshore wind farm, located in the German North Sea, 70 kilometres west of the island Sylt.

The main contractor for the foundations of this windfarm is Aarsleff Billfinger Berger Joint Venture (ABJV). The windfarm is owned by DanTysk Offshore Wind GmbH (DTOW).

Kees Jan Cordia, Managing Director of Workfox said: “The Seafox 5 has demonstrated to perform as initially designed without exceeding any risk and/or safety barriers due to the reliability of our offshore crew and the competency of our proven operational expertise as a company. In addition we would like to thank our client Aarsleff Billfinger Berger Joint Venture (ABJV) for the confidence and mature attitude in finalizing complex projects such as these.”

The Seafox 5 will arrive shortly in Esbjerg (Denmark) for demobilization and mobilization for her next assignment straight thereafter.

[mappress]

Press release, December 16, 2013; Image: Seafox

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Operations & MaintenanceWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Massachusetts Invests USD 4.2 Million to Boost Offshore Wind Workforce and Research
  2. 2Young Oysters Deployed on Two North Sea Cable Crossings
  3. 3Pacifico Energy Unveils EUR 860+ Million Investment in Two Offshore Wind Projects in South Korea
  4. 4Fourth Vard-Built CSOV Joins Windward Offshore Fleet

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free