No Use of External Generators at Anholt OWF (Denmark)

So far, it has often been necessary to use external diesel generators to secure the power supply in connection with the completion of installation and commissioning of offshore wind turbines because the connection to the power grid has not been ready. In the Anholt project, all wind turbine position

1 minutes read

So far, it has often been necessary to use external diesel generators to secure the power supply in connection with the completion of installation and commissioning of offshore wind turbines because the connection to the power grid has not been ready.

In the Anholt project, all wind turbine positions have been energised at an early stage, and therefore, it has been possible to install and energise all wind turbines without using external generators.

As the external generators are both heavy to handle and need regular inspection and fuel supply, it has been possible to save resources for both transport and expenses for fuel by using the existing grid connection.

However, as a precaution, 20 used generators had been purchased in case of technical problems, but the generators have not been used.

[mappress]

Press release, June 10, 2013; Image: dongenergy

Advertisement

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.