Busy Summer at Anholt OWF, Denmark

Even though the wind turbine installation is expected to be completed in May, the activities in terms of wind turbine commissioning and wind farm completion will still be hectic during the summer. Small service vessels will transport the numerous technicians inside the wind farm for them to complete

1 minutes read

Even though the wind turbine installation is expected to be completed in May, the activities in terms of wind turbine commissioning and wind farm completion will still be hectic during the summer.

Small service vessels will transport the numerous technicians inside the wind farm for them to complete the commissioning of the wind turbines and put them into operation one by one. Parallel to this activity, all wind turbines will be inspected after the first 500 operating hours.

The cable protection in the wind farm will be completed in summer 2013. All cables between the wind turbines and the substation have been flushed one metre into the seabed. However, at some positions, it has not been possible to sufficiently flush the cables into the seabed – either because the subsoil has been too hard or because of stones at the seabed. To secure cable protection also at these positions, a stone layer has been laid out.

[mappress]

Press release, May 3, 2013; Image: DONG Energy

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.