Advertisement

Wind Farm Update

about 14 years ago

‘Victoria Mathias’ Installs First Foundations at Nordsee Ost Offshore Wind Farm (Germany)

The first foundations at the Nordsee Ost offshore wind farm have been installed. The main crane of the Victoria Mathias lifts the 550-tonne steel foundations into the water. Whith roughly 40- to 50-metre-long steel piles the foundations are fixed into the seafloor. Then a hydraulic hammer knocks the

1 minutes read

The first foundations at the Nordsee Ost offshore wind farm have been installed.

The main crane of the Victoria Mathias lifts the 550-tonne steel foundations into the water. Whith roughly 40- to 50-metre-long steel piles the foundations are fixed into the seafloor. Then a hydraulic hammer knocks them 40 metres into the earth.

After that the foundations are aligned horizontally before being finally anchored in place with special concrete.

[mappress]

Press release, December 19, 2012; Image: RWE

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.