In just 16 days, during the second visit to the Global Tech I construction site, three more foundations were installed. The installation vessel INNOVATION proved to be extremely reliable in installation of the tripod foundations in 40 meters water depth. Arjen Schampers, Technical Director of Global

1 minutes read

In just 16 days, during the second visit to the Global Tech I construction site, three more foundations were installed.

The installation vessel INNOVATION proved to be extremely reliable in installation of the tripod foundations in 40 meters water depth.

Arjen Schampers, Technical Director of Global Tech I Offshore Wind GmbH stated: “We are proud of our offshore team that installed the first foundations so superbly. Now, it is time to take up the experiences of the first two trips and improve the installation processes continuously. We have built the first foundations in less than three days respectively, and are convinced that we can speed up the construction process even further. “

Global Tech I plans to install all foundations by summer of 2013, and to have this offshore wind farm fully operational by the end of 2013.

[mappress]

Offshore WIND staff, November 22, 2012; Image: globaltechone

Advertisement

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.