Long Pause Blurs Balance of Wind Farm Baltic 1 (Germany)

The four-week break in the fall accident has marred the balance of the first German offshore wind farm in the Baltic Sea “Baltic I”. “Generating electricity from the September 17th to October 15th was very good and was on schedule, “said the spokeswoman of the energy group EnBW, Friederike Eggstein.

1 minutes read

The four-week break in the fall accident has marred the balance of the first German offshore wind farm in the Baltic Sea “Baltic I”.

“Generating electricity from the September 17th to October 15th was very good and was on schedule, “ said the spokeswoman of the energy group EnBW, Friederike Eggstein.

In November there was very little wind, but the December was again very productive. EnBW’s accurate figures are unknown due to the business reasons.

The wind farm was shut down in September for maintenance, however it did not proceed with the electricity production on September 15 as planned. An official appointed for the maintenance work tug had rammed into the substation. Therefore the substation had to be checked.

[mappress]

Offshore WIND staff, December 26, 2011; Image: enbw

Advertisement

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.