offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Jumbo Offshore to Install 111 Transition Pieces for Anholt Offshore Wind Farm (Denmark)
Wind Farm Update

August 29, 2011 · about 15 years ago

Jumbo Offshore to Install 111 Transition Pieces for Anholt Offshore Wind Farm (Denmark)

MT Højgaard has awarded Jumbo Offshore the transport and installation contract for all of the 111 Transition Pieces (TP’s) for the Anholt Offshore Wind Farm (Denmark). The 400 MW wind farm is currently being developed by DONG Energy. The Anholt Wind Farm is located in the ‘Kattegat’, near Anholt Isl

2 minutes read
  • LinkedIn
  • X
  • Email

MT Højgaard has awarded Jumbo Offshore the transport and installation contract for all of the 111 Transition Pieces (TP’s) for the Anholt Offshore Wind Farm (Denmark). The 400 MW wind farm is currently being developed by DONG Energy.

The Anholt Wind Farm is located in the ‘Kattegat’, near Anholt Island, and will be the largest offshore wind farm in Denmark. One of Jumbo’s DP2 Offshore Heavy Lift Vessels will install the TP’s on pre-installed monopiles, starting April 2012.

Anholt is a result of Danish government policy, which aims for a society independent of fossil fuels. In 2020, 30% of gross consumption should come from renewable energy. For the Anholt contract, the TP’s will be loaded at Bladt Industries (Aalborg, Denmark). Every TP weighs approx. 200 t, is 17 m tall and has a diameter of approx. 5.5 m.

Mobilization

Mobilization is planned in Rotterdam (The Netherlands) early April 2012. The mobilization will include a motion compensated access bridge (for safe access to the TP when the vessel is on DP), a grout plant, a purpose-built lifting beam, two passive lifting compensators of in-house design, grillages and seafastenings. The two 900 t Huisman mast cranes will be re-reeved to their project specific configuration.

Method

For Jumbo, the contract is a recognition of the safe and efficient TP-installation works for the Greater Gabbard Offshore Wind Farm (UK). Jumbo’s all-in-one installation method will be largely repeated for the Anholt contract. This method consists of loading 9 TP’s at a time, transport them to the site and install them.

‘Jumbo’s installation method is a great match for this project and we are looking forward to working with them on the installation of the Transition Pieces on Anholt Offshore Wind Farm’ , says Kim Reinhard Andersen, Energy & Resources Director at MT Højgaard. When the 111 foundations are in place, MT Højgaard will have installed a total of 560 offshore windmill foundations, which is more than any other contractor in the world.

[mappress]

Source: jumboshipping, August 29, 2011

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Wind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Four Baltica 2 Offshore Substations Set Sail from Vietnam to Poland
  2. 2X1 Wind Closes Strategic Funding Round Ahead of 8.5 MW Floater Deployment
  3. 3RWE, Masdar Team Up for 2027 German Offshore Wind Auctions
  4. 4European Project Completes First Tests of Modular Drivetrain for Offshore Wind Turbines Beyond 15 MW

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free