Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›Seajacks Announces Zaratan Construction Summary (UK)
News

August 17, 2011 · about 15 years ago

Seajacks Announces Zaratan Construction Summary (UK)

In February 2010 Seajacks entered into a contract with GustoMSC to provide the Basic Design Package for two purpose built wind farm installation vessels. In June 2010 Seajacks entered into a contract with Lamprell shipyard to build these new vessels and Seajacks will take delivery of the first new-b

1 minutes read
  • LinkedIn
  • X
  • Email

In February 2010 Seajacks entered into a contract with GustoMSC to provide the Basic Design Package for two purpose built wind farm installation vessels.

In June 2010 Seajacks entered into a contract with Lamprell shipyard to build these new vessels and Seajacks will take delivery of the first new-build, Seajacks Zaratan, in May 2012, and the additional new-build shortly thereafter.

These self-propelled jack-ups have been designed specifically to service the wind farm installation market in the harsh operating environment of the North Sea, as well as to provide services to the oil and gas industry. The vessels will be a modified version of the MSC NG5500 design, which incorporates a fully redundant DP2 propulsion system, accommodations for 90 persons, and an 800T leg encircling crane designed by MSC.

Seajacks Zaratan Construction Summary – 11/08/2011

STRUCTURAL

Hull:

Spud Cans:

Legs:

Main Deck:

Accommodation:

Foundations:

Cable Trays:

Electric Cable:

Commenced running 690V cable on 2/8/11

Machinery Installation:

The following have been installed:-

Main equipment received on site and stored: –

Pipe work:

800T Crane:

Auxiliary Cranes:

Jacking System:

Vessel still on schedule for May 2012 delivery

[mappress]

Source: seajacks, August 17, 2011

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

News

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1IFM Investors to Acquire Majority Stake in UK Port Operator ABP
  2. 2TenneT and NKT Jointly Explore Offshore Cable Decommissioning
  3. 3GEOxyz Conducting Seabed Survey at East Anglia Two Offshore Wind Site
  4. 4US Gov’t Seeks New Review of US Wind’s Maryland Project

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free